Built in 1961 and opened in 1962, the Port Credit Library is located at the eastern shore of the Credit River just north of Lake Ontario in Mississauga, Ontario. In 2011, as part of the Mississauga Public Libraries Project, the Port Credit Library in particular was one of three Mississauga public libraries to undergo major renovations and additions, which was part of a larger retrofitting and revitalizing initiative for their distinct mid-century modernist structures for a 21st century audience.
In 2016, it was discovered that the concrete foundation of the Port Credit Library needed significant repairs. The contractor for the project proposed an original solution that called for the repair of the existing concrete caissons. This solution would have required significant excavation on either side of the caissons to replace the concrete pad that supported the existing grade beam. This work would have to be done before the actual caisson repairs could be completed, which would have required significant time and expense. A major challenge with this solution was the library was originally built on top of a historic landfill that had a high-water table. This meant that the original concrete repair solution proposed for the project was no longer an option. They needed to find a way to stabilize the structure with minimum subsurface disturbance. At this point in the project, Techno Metal Post Hamilton-Durham (TMPHD) was contacted and a helical pier solution was proposed.
Once TMPHD was contracted to complete the work, we received all the necessary information and completed pier tests around the perimeter of the property. This was done to make sure we could drill through the buried garbage in the landfill and achieve the required bearing capacities. Working with the Techno Metal Post Engineering Department, we developed several solutions to keep the integrity of the building intact without any major modifications to the library. All proposed options were discussed with the City of Mississauga engineer team, and the final solution was agreed to and TMPHD started the work.
The helical pier solution required stabilization of the library building foundation using piers on either side of the existing caissons to support the existing concrete beams under the building.
A steel I-beam was then installed between the piers running under the building to the outside.
Once the beams were in place, the leveling cap plates were installed to ensure the concrete beams were well-fitted to the steel beams. To hide the piers and the steel beams on the outside of the library, custom boxes were designed to cover them up to keep the original architectural structure and design of the building intact.
In the end, a cost-effective and safe solution was carried out without changing the look of the Port Credit Library and allowing for it to remain open to the public while the work was being done. A major success for this project was that little to no subsurface soils needed to be disturbed during the restoration work.
Year: 2016
Dealer: Derek Hofrichter and Roger Lauzon TMP Hamilton-Durham
Client: Port Credit Library, City of Mississauga
Location address: 20 Lakeshore Road East, Mississauga, ON.
Engineering firm: AMEC Foster Wheeler, Environment and Infrastructure
General contractor: JASS Construction
Project objectives: To find a cost-effective solution to stabilize the library foundation due to deteriorated concrete. All to be completed without closing the library or changing the architectural look of the structure.
Specific challenges:
Advantages over other methods:
Soil type: Earth fill, and landfill contents, silty clay till
Installation time: 3 weeks
Number of people on site: 3
Materials used:
Equipment used:
Bearing capacity: 70 kN (15 750 lb) per pier (load mentioned on plan realized by Brook and Banz, Architects, June 27, 1961)
Engineer’s specific requirements: Drill piers until native soil reached and required bearing capacity achieved.
Average depth of piers: piers installed and drilled into the ground on an average depth of 40 feet
Specific details of the structure on piers: Mid-20th Century public library on concrete beams
HELICAL FOUNDATIONS
WITH TECHNO METAL POST, IT'S FAST AND EASYTechno Metal Post makes life easier for anyone with a construction project that requires a foundation in almost any type of soil.